CASE 1: McWhinney Office Building , Colorado (1997-1998 )
4D model (Pre-construction):
Benefits:
|
|
|
|
CASE 2: Sequus Pharmaceuticals Pilot Plant, Menlo Park (1997- 99 )
3D model (Design Development):
- MEP design coordination
- Automated quantity takeoff
4D model (Early Construction):
- Coordinating MEP installation with equipment installation
Benefits:
- No MEP change order; 60% fewer RFI
|
|
|
|
CASE 3: Experience Music Project, Seattle (1998 - 2000 )
3D model (Schematic Design – Detailed Design)
4D model (Construction)
- Sequencing in tight quarters of skin
Benefits:
- Lessened trade stacking, interference
|
|
|
|
CASE 4: Paradise Pier, Disney California Adventure, LA (1998 - 99 )
3D model (Schematic Design – Design Development)
- Visualized finished project & Ride sim.
4D model (Construction Document's)
- Strategic planning of proj. milestones
- Sequencing of bid packages
- Coordinating track erection with testing
Benefits:
- Engaged 400 stakeholders in 2 months
- Bid results: within +/- 2.5% of budget
- Contractors understood project scope & challenges within 48 hrs
|
|
|
|
CASE 5: Helsinki University of Technology Auditorium-600 (HUT-600) Project, Helsinki (2000 - 02 )
3D model (Conceptual planning)
- Cost estimating
- Lighting design & energy simulation
4D model (Schematic Design)
- Virtual walk-through of spatial designs
- Comprehension of construction sequences
Benefits:
- Promised 10-15% savings of total building costs
- Promised 5-25% savings of Life Cycle Costs
- 80% reduction in time on cost estimate
- 50% time savings in design document phase
|
|
|
|
CASE 6: Baystreet, Emeryville (2000 - 2002 )
4D model (Early Construction)
- Accelerating steel erect. in theater area to enable opening before Christmas
- Site logistics, e.g., how to get concrete up five floors inside tight quarters
Benefits:
- Saved 3 weeks, 7% off original schedule
|
|
|
|
CASE 7: Genentech FRCII, South San Francisco (2001 - 2003 )
3D model (Early Construction)
- Planning of the ideal teledata routing
- Cost tracking of subs' proposal, billings
- Space rearrange during building operation
4D model (Early Construction)
- Coordination of MEP installation
Benefits:
- Identified opportunities to reduce change order
|
|
|
|
CASE 8: Walt Disney Concert Hall Project, Los Angeles (1999 - 2003 )
3D model (Schematic Design)
- Visualization of geometric complexity
- Dimensional control & fabrication
Four 4D models (Pre-construction)
- Improving upon the construction schedule
- Detecting constructability problems
- Planning of lay-down, crane locations, hoisting methods, scaffolding strategy & instl. of complex ceiling
Benefits:
- Saved time to communicate schedule
|
|
|
|
CASE 9: Hong Kong Disneyland , Hong Kong (2001 - 2006 )
3D model (Early Design)
4D model (Schematic Design)
- Coordination of phased handover from site work to constr. mobilization
-
Strategic planning of constr. milestone
Benefits:
- Resolved accessibility issues and space conflicts for phased handover
|
|
|
|
CASE 10: Pioneer Courthouse Seismic Upgrade and Rehabilitation Project , Portland (2001 - 2003 )
4D model (50% Construction Documents)
- Assisted owner in comprehending the construction sequencing of base-isolation as specified by the structural engineers
Benefits:
- “Proof-of-concept” for the use of 4D technologies in GSA
|
|
|
|
CASE 11: Ray and Maria Stata Center Project, Boston (2000 - 2004 )
3D model (Early Design)
- Visualization of geometric complexity
Three 4D models (Early Construction)
- Communicating GC's schedule to subs
- Constr. Sequencing between two towers
- Planning of access & staging areas
- Illustrating the need of temporary exterior enclosure for weather protection
|
|
|
|
CASE 12: Banner Health Good Samaritan Hospital , Phoenix (2002 - 2004)
4D model (Pre-construction)
- Synchronizing facility operation with construction
- Detecting potential interferences & risks of site safety, e.g., cranes within the flight path of medevac helicopter
Benefits:
- 4D cost: < 0.05% of total project costs
|
|
|
|
CASE 13: California Academy of Science Project , San Francisco (2003 - 2006 )
3D model (50% Construction Documents)
- Detecting design errors & inconsistency
- Estimating / tracking subs' proposals
4D model (Design Development)
- Comparison of concrete roof alternative to the original steel roof system
4D model (Pre-construction)
- Planning of pouring sequences for the concrete foundation
|
|
|
|
CASE 14: Terminal 5 of London 's Heathrow Airport , London (2003 - 2007 )
3D model (Detailed Design)
- Coordinating drawing production of detailed rebar design with procurement
- Design coordination of the reinforcement at the tunnel eye
Benefits:
- Minimize the number of review sessions
- Reduced batch sizes of rebar drawings
- Reduced procurement lead-time on rebar from 2 weeks to 3 days
- Reduced onsite RFI's by 80%
|
|
|
|
CASE 15: 4-D virtual building in Sweden , Stockholm (2002 - 2003 )
4D model (Post-construction)
- Test of traditional form work system vs. permanent form work& pre-installed rebar
- Detailed analysis of daily operation of form work, rebar, & concrete tasks in the 4D model
- Comparison of construction alternatives in a 4D CAD environment
|