aaaaaaaaaaaaaaaaaCase Studies on the Implementation & Benefits of 3D and 4D CAD

 

 

CIFE RESEARCH 2004 - 05

Home

Example Cases

Framework

Contacts

 

 

 

CASE 1: McWhinney Office Building , Colorado (1997-1998 )

4D model (Pre-construction):

  • Improved a CPM schedule

Benefits:

  • Saved 2 weeks

CASE 2: Sequus Pharmaceuticals Pilot Plant, Menlo Park (1997- 99 )

3D model (Design Development):

  • MEP design coordination
  • Automated quantity takeoff
4D model (Early Construction):
  • Coordinating MEP installation with equipment installation

Benefits:

  • No MEP change order; 60% fewer RFI

CASE 3: Experience Music Project, Seattle (1998 - 2000 )

3D model (Schematic Design – Detailed Design)

  • Visualized curved skin

4D model (Construction)

  • Sequencing in tight quarters of skin
Benefits:
  • Lessened trade stacking, interference

CASE 4: Paradise Pier, Disney California Adventure, LA (1998 - 99 )

3D model (Schematic Design – Design Development)

  • Visualized finished project & Ride sim.

4D model (Construction Document's)

  • Strategic planning of proj. milestones
  • Sequencing of bid packages
  • Coordinating track erection with testing

Benefits:

  • Engaged 400 stakeholders in 2 months
  • Bid results: within +/- 2.5% of budget
  • Contractors understood project scope & challenges within 48 hrs

CASE 5: Helsinki University of Technology Auditorium-600 (HUT-600) Project, Helsinki (2000 - 02 )

3D model (Conceptual planning)

  • Cost estimating
  • Lighting design & energy simulation

4D model (Schematic Design)

  • Virtual walk-through of spatial designs
  • Comprehension of construction sequences

Benefits:

  • Promised 10-15% savings of total building costs
  • Promised 5-25% savings of Life Cycle Costs
  • 80% reduction in time on cost estimate
  • 50% time savings in design document phase

CASE 6: Baystreet, Emeryville (2000 - 2002 )

4D model (Early Construction)

  • Accelerating steel erect. in theater area to enable opening before Christmas
  • Site logistics, e.g., how to get concrete up five floors inside tight quarters

Benefits:

  • Saved 3 weeks, 7% off original schedule

CASE 7: Genentech FRCII, South San Francisco (2001 - 2003 )

3D model (Early Construction)

  • Planning of the ideal teledata routing
  • Cost tracking of subs' proposal, billings
  • Space rearrange during building operation

4D model (Early Construction)

  • Coordination of MEP installation

Benefits:

  • Identified opportunities to reduce change order

CASE 8: Walt Disney Concert Hall Project, Los Angeles (1999 - 2003 )

3D model (Schematic Design)

  • Visualization of geometric complexity
  • Dimensional control & fabrication

Four 4D models (Pre-construction)

  • Improving upon the construction schedule
  • Detecting constructability problems
  • Planning of lay-down, crane locations, hoisting methods, scaffolding strategy & instl. of complex ceiling

Benefits:

  • Saved time to communicate schedule

CASE 9: Hong Kong Disneyland , Hong Kong (2001 - 2006 )

3D model (Early Design)

  • Energy simulation

4D model (Schematic Design)

  • Coordination of phased handover from site work to constr. mobilization
  • Strategic planning of constr. milestone

Benefits:

  • Resolved accessibility issues and space conflicts for phased handover

CASE 10: Pioneer Courthouse Seismic Upgrade and Rehabilitation Project , Portland (2001 - 2003 )

4D model (50% Construction Documents)

  • Assisted owner in comprehending the construction sequencing of base-isolation as specified by the structural engineers

Benefits:

  • “Proof-of-concept” for the use of 4D technologies in GSA

CASE 11: Ray and Maria Stata Center Project, Boston (2000 - 2004 )

3D model (Early Design)

  • Visualization of geometric complexity

Three 4D models (Early Construction)

  • Communicating GC's schedule to subs
  • Constr. Sequencing between two towers
  • Planning of access & staging areas
  • Illustrating the need of temporary exterior enclosure for weather protection

CASE 12: Banner Health Good Samaritan Hospital , Phoenix (2002 - 2004)

4D model (Pre-construction)

  • Synchronizing facility operation with construction
  • Detecting potential interferences & risks of site safety, e.g., cranes within the flight path of medevac helicopter

Benefits:

  • 4D cost: < 0.05% of total project costs

CASE 13: California Academy of Science Project , San Francisco (2003 - 2006 )

3D model (50% Construction Documents)

  • Detecting design errors & inconsistency
  • Estimating / tracking subs' proposals

4D model (Design Development)

  • Comparison of concrete roof alternative to the original steel roof system

4D model (Pre-construction)

  • Planning of pouring sequences for the concrete foundation

CASE 14: Terminal 5 of London 's Heathrow Airport , London (2003 - 2007 )

3D model (Detailed Design)

  • Coordinating drawing production of detailed rebar design with procurement
  • Design coordination of the reinforcement at the tunnel eye

Benefits:

  • Minimize the number of review sessions
  • Reduced batch sizes of rebar drawings
  • Reduced procurement lead-time on rebar from 2 weeks to 3 days
  • Reduced onsite RFI's by 80%

CASE 15: 4-D virtual building in Sweden , Stockholm (2002 - 2003 )

4D model (Post-construction)

  • Test of traditional form work system vs. permanent form work& pre-installed rebar
  • Detailed analysis of daily operation of form work, rebar, & concrete tasks in the 4D model
  • Comparison of construction alternatives in a 4D CAD environment
TOP