|
SUPERVISORY CONTROL & DATA ACQUISITION
SYSTEM (SCADA)
History
In 1993 it was determined that a Supervisory
Control & Data Acquisition System (SCADA) system was
needed to monitor the campus electrical supply and distribution system. A study was
conducted to determine which SCADA system would be most appropriate for Stanford University
Power Systems.
We reviewed other utilities' SCADA and wall Map systems such as PG&E, Palo
Alto, Santa Clara and Berkeley. In addition, we contacted numerous vendors
in order to better understand the different technologies available. Most
of the packaged systems involved the purchase of a complete SCADA system as
opposed to the method of using single meters as the basic component.
We were aware that strategically placing these meters both in switch gear at the
substations and building switchgear; an effective instant evaluation could be
made regarding the status of the electrical power distribution system.
In 1994 the Utilities Division started
installation of the campus SCADA system using Intelligent Electronic Devices (IEDs)
and a DOS based SCADA software package. The Energy
Management Control Systems (EMCS) group, which is a department in the Utilities Division, also needs
data from building meters. The IEDs provide
communications to the SCADA software as well as an analog output signal
(proportional to kW) which is read by the building EMCS.
The building EMCS (a
Rosemont system) records this signal to track electrical energy demand and Kilo
Watt Hours (KWH).
The SCADA software is a
graphical package using a Window NT Operation System. The system,
manufactured by Power Measurement Ltd (PML), provides the programming necessary
to incorporate actual AutoCAD campus maps and diagrams, and to display real time
information on top of the graphic background. Items such as: power
system parameters, breakers and switches status, alarms, event logs &
historical data logs; can be overlaid on the AutoCAD Single-Line
Diagram.
Additionally, this system allows the
Facilities Operations - High Volt Technicians to
view the big picture (a section of campus), and then tunnel down to a detailed
view ( a single-line) as needed. SCADA automatically generates alarms and
monthly energy reports and is easily expandable as the needs grow. The new
system is extremely flexible and is completely expandable as IED meters are added.
Benefits
Present
Benefits
The
University needs have grown and the demands for reliable and accurate
performance and trend data have increased. High Volt Technicians need to
be able to remotely and instantaneously, identify electrical power loop feeder
sections that are affected, and respond accordingly. As discussed, when a
particular section of the distribution system goes down, the operators are provided with instant information. This enables the system operators to
provide individual building managers, researchers, department chairs and others,
information on the problem. In addition, the engineers are able
to examine historical data for load trending, planning and improving
system performance.
In addition,
the following functions are being utilized more and more as the SCADA system is
expanded across campus.
-
Manual meter reading is being replaced with
automatic reporting
-
Real time alarms and data give operators the
information they need to respond quickly.
-
The Utilities Division can be
proactive in providing quality information to its customers.
Long
Term Benefits and Future Needs
Power System Operators need to be able to continue to remotely and
instantaneously, identify electrical power system failures at any
location in the distribution system. Accurate real time alarming
and historical information is needed to continually meet the needs of
a diverse community of energy users. A continuation of the
demands for high reliability and accurate performance and trending
data is paramount.
Stanford
has already been experimenting with the web based metering and plans to
incorporate, and design custom features with off the shelf web based tools.
This will allow users within the university community to access specific
information by using a web browser instead of expensive third party software (e.g., energy consumption
report, performance data, etc...).
Summary
It is
considered imperative that Stanford University become fully aware of the
disposition of the Electrical System at all times in order to serve the academic
mission with the least amount of disruptions. Stanford requires
accurate real-time alarming and historical information to continually
meet the needs of a diverse community of energy users. We need to prevent
outages and other power problems proactively. We have acquired a solid
communications and highly reliable SCADA system.
SCADA
System in Action
Fault
Location
Prior
to 1993, the method used to determine the magnitude of a campus power
failure such as which buildings were affected and what should be first priority to
restore power to were determined by a combination of waiting, hoping,
guessing, triangulation and luck.
A
triangulation scenario:
A
power failure on the campus would usually start with a call being received
from Maintenance Customer Service (MCS) or a building manager stating that a
building, ( in some cases a number of buildings) had lost its electrical power.
Not knowing which branch of the circuit had failed; High-Volt Electricians would
wait for a second call identifying another building
power outage. Eventually, when a number of buildings
without power were identified, by using a simple method of triangulation could be
used to
determine which area of the distributions system had failed. This would be an elaborate
procedure, sometimes taking several
hours. High-Volt crews would be dispatched along the route of the distribution
(all of which is underground at Stanford) and would selectively remove vault
and manhole covers, observing the fault indicators on the distribution cables.
In time, the cause of these multiple building power failures were becoming more
difficult to locate, consequently, fault location time, and subsequent
restoration time could be several hours. With the installation of SCADA
technology, the excessive time spent investigating faults and problems is reduce
substantially.
Outage
Record
Post
incident analysis is required to prevent reoccurrence of similar outages and
power failures.
Position
and Status of Breakers
Multiple
use of HV switch contacts that are connected to the system, gives the system
operators the ability to obtain instant and remote status changes.
Amperage
on Feeder Cables
In
addition to the fault location requirement, the High Volt Technicians needed to
able to record and evaluate the current use of specific distribution cables.
Switching operations required daily reports to enable them to transfer load to
other feeders. In the past obtaining this information required sending an
electrician to the substation to record the feeder ammeters, a time consuming
event.
Substation
Battery Status
Five
banks of batteries are installed for breaker control, relay protection and
tripping circuits. Loss of the critical function of
the battery system can be devastating for a switchgear breaker unit and inability
to trip a faulted circuit can be a disaster. Setting low voltage limits
that alarm instantly, warns the maintenance personnel who can respond quickly
and avert a major problem.
Switching
and Paralleling Operations
Confirmation
of the physical change in operator switch position was not available prior to
the use of remote SCADA applications.
Power
Quality
As
needed, generally after an event, or upon query from building users power users
power quality records are requested.
Substation
Security Fires and Door Alarms
Early
on in the design of the SCADA application, it was determined that fire/smoke
detectors were needed in all substation switch gear rooms. This function,
along with door alarm contacts, provides the system operators with the ability
to respond instantly to these types of events.
Substation
Primary Transformer Status
Most
substation transformer status alarms and events are monitored by the system.
The annunciation and display of alarm conditions ensures timely investigation of
the problem. Remedial action can prevent future equipment damage and power
outages.
Emergency
Generator & Power Available Status
Stanford
has an ongoing program to replace the Cogeneration Plant emergency feeders
stand-alone generators. Emergency generator breaker running and transfer
switch transferred status is imperative to understanding the specific
availability of the emergency source. These monitored events provide the
added assurance that all systems are working correctly.
Breaker
Position Status at Building Voltage Level
Auxiliary
breaker contacts on the main building, 208/480-Volt service boards are connected
into the SCADA system. These enable High Volt Technicians to be informed of a
single or multiple building area power failure.
Hospital
and Medical School Emergency Services Status
The Hospital
emergency power feeders from the Cogeneration Plant are monitored to confirm the
availability of the services, on a continual basis; this prevents the
remote possibility that the service is not available. As mentioned
earlier, Stanford is presently designing a system of stand-alone generators to
replace the Cogeneration Plant emergency feeders.
|