Analysis of Current 4D Practice
| Meeting Location: | Large Desktop/CAVE 4D environment |
| Physical Layout: | ![]() |
| Meetings Observed: | 3 |
| Length of Meetings: | 45-60 minutes |
| Participants: | Construction Management Team (5), Bidding General Contractor (5-15) |
| Goal of Meeting: | To introduce potential bidding general contractors to the project, point out potential problem areas, and allow them to ask questions about the project |
|
Question |
Response |
Target
Information |
||||
|
Question |
Type |
Description
|
Form |
Source |
Rel.
Type |
Reliability
|
|
GC: Where's access to site? |
Descr. |
The CM points to the
area of the site where access is. |
· Verbal · Physical · Visual
|
· Access
diagrams · Contract · Physical
location |
Req.-Time-Space |
Medium |
|
GC: Can
we use the space by this building? |
Descr. |
CM: The area is only
available for a 1-month period because it's part of another project. |
· Verbal · Physical |
· GC schedule for other project · |
Space-Time |
Medium |
|
GC:When will the wave machine be
available? |
Descr. |
Vendor says it will be
available XXX. |
· Verbal |
· Procurement information · Contract |
Time-Space |
|
|
GC: What is driving the finish times for the rides? |
Expl. |
Stepped turnover to
operations |
·Verbal |
· Not
documented, overall strategy |
|
|
|
GC: Can
we move the start dates of the rides? |
Pred. |
Yes, but…. |
· Verbal · Physical |
· Vendor information · Ride procurement · Fabricator schedule |
Spatial |
|
Analysis of Current Practice
| Meeting Location: | Conference room |
| Physical Layout: | ![]() |
| Meetings Observed: | 6 |
| Length of Meetings: | 2 hours |
| Participants: | Construction Management Team (3-5), General
Contractor (3-8) |
| Goal of Meetings: | To review the schedule and/or
schedule status of the general contractor |
|
Question |
Response |
Target
Information |
|||||
|
Question |
Type |
Description
|
Form |
Source |
Rel.
Type |
Cost
|
Reliability
|
|
GC: When do we have access to XXX? |
Descr. |
The project manager
pulled out a 2D layout of the site annotated with areas and their
availability dates based on the contract |
· Verbal · Physical · Visual: Text Annotation
on 2D Diagram |
· Contract-in
textual form |
Contractual Date-Site
Area |
$$$ Someone has to produce
the 2D diagram and update it according to actual progress on site |
?? |
|
CM: What
sections of the walls do these numbers refer to? (lagoon 4, lagoon 3, etc) |
Descr. |
Team points to drawing
on wall (that is large-scale and not detailed for the sections referred to) |
Verbal Physical |
· |
Spatial |
|
|
|
CM: Where are
you placing the crane for erection of XXX? |
Descr. |
Points to 2D layout and
location of crane |
Verbal Physical |
· None |
Space-Time |
|
|
|
Who's doing the work for these activities? |
Descr. |
A is doing X, B is
doing Y,…. |
Verbal |
· Schedule
code |
Resource-activity |
|
|
|
Does this
meet the contractual milestone? |
Eval. |
Response is quickly
stated as 'yes' |
Verbal |
· Contract · GC
schedule |
Contract-Schedule (time-time) |
Search through contract
information and schedule info |
As information in
schedule changes, this may change |
|
CM: Does the
schedule include the specified amount of time for curing? |
Eval. |
The team has to spend
time searching through the schedule and then determine whether their activity
durations account for the curing time. |
Verbal |
|
|
|
|
|
CM: Why are
you starting X facility at this date? |
Expl. |
Team points to drawing
on wall (that is large-scale and not detailed for the sections referred to) |
Verbal Physical |
|
|
|
|
|
CM: Have you
considered impact of this sequence on other work in this area? |
Pred. |
|
|
|
|
|
Very unreliable |
|
GC: Can we get access to the lagoon a week earlier? |
Pred. |
Project manager
informed the team that the dates noted on the diagram are 'contractual' dates
and that access could be provided earlier if the current work finishes early,
but could not answer definitively. |
Verbal |
· Turnover
Activities in GC #1 schedule · Breakdown
of Construction Areas for release by GC #1 |
Activity-Area |
$$$ |
|

Table 3: Analysis of Questions and Responses - Construction Information Workspace Practice
Meeting Location: Conference Room with Construction
Information Workspace
# of Meetings Observed: None
Length of Meetings: 2 hours
Participants: Construction Management Team (3-5), General
Contractor (3-8)
Goal of Meetings: To review the schedule and/or schedule status of the general contractor
|
Question |
Response |
Referenced
Information |
|||||
|
Question |
Type |
Description
|
Form |
Source |
Rel.
Type |
Cost
|
Reliability
|
|
GC: When do we have access to XXX? |
Descr. |
|
· Visual: |
· Contract-in
textual form |
Contractual Date-Site
Area |
$ Initial cost of
defining areas and relating to information in contract |
|
|
CM: What
sections of the walls do these numbers refer to? (lagoon 4, lagoon 3, etc) |
Descr. |
Team points to drawing
on wall (that is large-scale and not detailed for the sections referred to) |
Verbal Physical |
· |
Spatial |
|
|
|
CM: Where are
you placing the crane for erection of XXX? |
Descr. |
Points to 2D layout and
location of crane |
Verbal Physical |
· None |
Space-Time |
|
|
|
Who's doing the work for these activities? |
Descr. |
A is doing X, B is
doing Y,…. |
Verbal |
· Schedule
code |
Resource-activity |
|
|
|
Does this
meet the contractual milestone? |
Eval. |
Response is quickly
stated as 'yes' |
Verbal |
· Contract · GC
schedule |
Contract-Schedule (time-time) |
Search through contract
information and schedule info |
As information in
schedule changes, this may change |
|
CM: Does the
schedule include the specified amount of time for curing? |
Eval. |
The team has to spend
time searching through the schedule and then determine whether their activity
durations account for the curing time. |
Verbal |
|
|
|
|
|
CM: Why are
you starting X facility at this date? |
Expl. |
Team points to drawing
on wall (that is large-scale and not detailed for the sections referred to) |
Verbal Physical |
|
|
|
|
|
CM: Have you
considered impact of this sequence on other work in this area? |
Pred. |
|
|
|
|
|
Very unreliable |
|
GC: Can we get access to the lagoon a week earlier? |
Pred. |
Project manager
informed the team that the dates noted on the diagram are 'contractual' dates
and that access could be provided earlier if the current work finishes early,
but could not answer definitively. |
Verbal |
· Turnover
Activities in GC #1 schedule · Breakdown
of Construction Areas for release by GC #1 |
Activity-Area |
$$$ |
|